Grade-line result
Enter two sections and calculate.
Ready for an energy check
HGL is elevation plus pressure head. EGL adds velocity head.
Compare hydraulic grade and energy grade between two supplied sections with a Bernoulli energy balance.
Enter two sections and calculate.
HGL is elevation plus pressure head. EGL adds velocity head.
TOOL-009 computes HGL = z + p/γ and EGL = HGL + V²/(2g) at two supplied sections in canonical SI units.
The upstream energy grade is reduced by the supplied total head loss and compared with the downstream energy grade. The residual is reported as balanced within 1e-6 m, energy surplus or energy deficit.
For upstream z = 100 m, pressure head = 8 m and velocity = 2 m/s, downstream z = 98 m, pressure head = 8.1 m and velocity = 2.2 m/s, with 0.3 m supplied loss, the helper reports the two HGL/EGL values and the energy balance residual.
This closed draft compares user supplied sections. It does not solve a network HGL profile, surcharge, pipe sizing, pump or turbine work, minor-loss schedule, unsteady flow or code compliance.
SRC-BERNOULLI-GRADE-LINES-TOOL009-001